| PRESUPUESTO POR MANO DE OBRA Y GENERAL DE LA OBRA |
| (En Bolivianos) |
Cerramiento de vivienda |
| No. | Descripción | Unidad | Cantidad | P. Unitario | Subtotal |
|---|---|---|---|---|---|
| 1 | Maestro albaƱil | jrnl | 181.15 | 120.00 | 21,737.70 |
| 2 | Ayudante | jrnl | 182.23 | 45.00 | 8,200.24 |
| 3 | Ayudante (encofrador) | jrnl | 18.22 | 70.00 | 1,275.75 |
| 4 | Maestro encofrador | jrnl | 7.92 | 120.00 | 951.00 |
| 5 | Ayudante (fierrista) | jrnl | 18.22 | 70.00 | 1,275.75 |
| 6 | Maestro fierrista | jrnl | 7.92 | 120.00 | 951.00 |
| 7 | Capataz | jrnl | 0.37 | 150.00 | 54.75 |
| 8 | Maestro pintor | jrnl | 24.00 | 120.00 | 2,880.00 |
| 9 | Ayudante (pintor) | jrnl | 12.00 | 70.00 | 840.00 |
| Total | 38,166.19 | ||||
| Son: TREINTA Y OCHO MIL CIENTO SESENTA Y SEIS 19/100 Bolivianos | |||||