APU de PERGOLA 50cm altura PM90 exterior PM60 interior c/50cm
En :
| 1. MATERIALES | |||||
| Descripción | Unidad | Cantidad | Precio productivo | Costo total | |
| 22117 | Perfil esquinero de PVC 2.40 m | u | 1.50 | 4.00 | 6.00 |
| 23160 | Panel Muro METALPOL® PM60/D15/3PFL41.3/045/1.22x2.44 | u | 0.60 | 36.99 | 22.19 |
| 23161 | Panel Muro METALPOL® PM90/D15/3PFL63.5/045/1.22x2.44 | u | 0.70 | 53.48 | 37.44 |
| 23658 | Panel 12mm Oxido de Magnecio | u | 0.70 | 33.60 | 23.52 |
| 23659 | Tornillos DRYWALL P/BR (EP) #6-20X1" (250 und) | u | 0.15 | 7.50 | 1.13 |
| 23745 | MALLA 15cmx45m JUNTA RIGIDA (BLANCO) | rollo | 0.05 | 18.61 | 0.93 |
| 23781 | Masilla Base Coat 25Kg | u | 0.04 | 21.28 | 0.85 |
| Total materiales | 92.06 | ||||
| 2. MANO DE OBRA | |||||
| Descripción | Unidad | Cantidad | Precio productivo | Costo total | |
| 15849 | Instalador | Hora | 1.50 | 4.10 | 6.15 |
| 15868 | Maestro de Obra | Hora | 0.25 | 4.33 | 1.08 |
| Total mano de obra | 7.23 | ||||
| 3. EQUIPO, MAQUINARIA Y HERRAMIENTAS | |||||
| Descripción | Unidad | Cantidad | Precio productivo | Costo total | |
| 18102 | Andamio | Hora | 1.50 | 0.06 | 0.09 |
| Herramientas menores % | 5.00% | 0.36 | |||
| Total equipo, maquinaria y herramientas | 0.45 | ||||
| 4. GASTOS GENERALES Y ADMINISTRATIVOS |
| 5. UTILIDAD |
| 6. IMPUESTOS | ||
| Total Precio Unitario de PERGOLA 50cm altura PM90 exterior PM60 interior c/50cm | 99.74 | |
Especificaciones técnicas:
No hay especificaciones para esta actividad. Inicie sesión para editarla.