1. MATERIALES | |||||
Descripción | Unidad | Cantidad | Precio productivo | Costo total | |
15914 | Cemento Fuerte Tipo GU Saco 50 Kg - Holcim DISENSA | saco | 11.54 | 7.68 | 88.63 |
16008 | Tablero TRIPLEX CORRIENTE 1.22X2.44X12C | u | 0.35 | 26.05 | 9.12 |
18054 | Arena | m3 | 1.04 | 13.50 | 14.04 |
18055 | Ripio | m3 | 1.52 | 18.00 | 27.36 |
18056 | Agua | m3 | 0.35 | 0.85 | 0.30 |
18083 | Acero de refuerzo fc=4200kg/cm2 | kg | 70.00 | 0.81 | 56.70 |
18974 | Clavos 2", 2 1/2", 3", 3 1/2" | kg | 2.55 | 2.13 | 5.43 |
18975 | Alfajia 6x6x250 cm | u | 2.20 | 2.50 | 5.50 |
19623 | Plastiment BV-40 10 Kg - Sika DISENSA | u | 0.18 | 22.60 | 4.07 |
22034 | Puntal de madera de eucalipto | m | 4.20 | 1.12 | 4.70 |
Total materiales | 215.84 |
2. MANO DE OBRA | |||||
Descripción | Unidad | Cantidad | Precio productivo | Costo total | |
15837 | Peón | Hora | 17.16 | 4.05 | 69.50 |
15838 | Albañil | Hora | 2.86 | ||
15839 | Operador de equipo | Hora | 5.72 | 4.10 | 23.45 |
15868 | Maestro de Obra | Hora | 2.86 | 4.33 | 12.38 |
Total mano de obra | 105.33 |
3. EQUIPO, MAQUINARIA Y HERRAMIENTAS | |||||
Descripción | Unidad | Cantidad | Precio productivo | Costo total | |
18057 | Concretera 1 saco | Hora | 2.86 | 4.48 | 12.81 |
18058 | Vibrador de manguera | Hora | 2.86 | 4.06 | 11.61 |
Herramientas menores % | 5.00% | 5.27 | |||
Total equipo, maquinaria y herramientas | 29.69 |
4. GASTOS GENERALES Y ADMINISTRATIVOS |
5. UTILIDAD |
6. IMPUESTOS | ||
Total Precio Unitario de Colector H.A. S=1.20x1.80 M | 350.87 |
Especificaciones técnicas:
RENDIMIENTO: 2.86 Horas/m