APU de Colector H.A. S=1.00x1.40 M
En :
1. MATERIALES | |||||
Descripción | Unidad | Cantidad | Precio productivo | Costo total | |
15914 | Cemento Fuerte Tipo GU Saco 50 Kg - Holcim DISENSA | saco | 8.65 | 7.68 | 66.43 |
16008 | Tablero TRIPLEX CORRIENTE 1.22X2.44X12C | u | 0.30 | 26.05 | 7.82 |
18054 | Arena | m3 | 0.78 | 13.50 | 10.53 |
18055 | Ripio | m3 | 1.14 | 18.00 | 20.52 |
18056 | Agua | m3 | 0.26 | 0.85 | 0.22 |
18083 | Acero de refuerzo fc=4200kg/cm2 | kg | 60.00 | 0.81 | 48.60 |
18974 | Clavos 2", 2 1/2", 3", 3 1/2" | kg | 2.28 | 2.13 | 4.85 |
18975 | Alfajia 6x6x250 cm | u | 1.90 | 2.50 | 4.75 |
19623 | Plastiment BV-40 10 Kg - Sika DISENSA | u | 0.12 | 22.60 | 2.71 |
22034 | Puntal de madera de eucalipto | m | 3.80 | 1.12 | 4.26 |
Total materiales | 170.69 |
2. MANO DE OBRA | |||||
Descripción | Unidad | Cantidad | Precio productivo | Costo total | |
15837 | Peón | Hora | 12.66 | 4.05 | 51.27 |
15838 | Albañil | Hora | 2.11 | ||
15839 | Operador de equipo | Hora | 4.22 | 4.10 | 17.30 |
15868 | Maestro de Obra | Hora | 2.11 | 4.33 | 9.14 |
Total mano de obra | 77.71 |
3. EQUIPO, MAQUINARIA Y HERRAMIENTAS | |||||
Descripción | Unidad | Cantidad | Precio productivo | Costo total | |
18057 | Concretera 1 saco | Hora | 2.11 | 4.48 | 9.45 |
18058 | Vibrador de manguera | Hora | 2.11 | 4.06 | 8.57 |
Herramientas menores % | 5.00% | 3.89 | |||
Total equipo, maquinaria y herramientas | 21.90 |
4. GASTOS GENERALES Y ADMINISTRATIVOS |
5. UTILIDAD |
6. IMPUESTOS | ||
Total Precio Unitario de Colector H.A. S=1.00x1.40 M | 270.30 |
Especificaciones técnicas:
RENDIMIENTO: 2.11 Horas/m