APU de Colector H.A. S=1.00x1.00 M
En :
| 1. MATERIALES | |||||
| Descripción | Unidad | Cantidad | Precio productivo | Costo total | |
| 15914 | Cemento Fuerte Tipo GU Saco 50 Kg - Holcim DISENSA | saco | 7.57 | 7.68 | 58.14 |
| 16008 | Tablero TRIPLEX CORRIENTE 1.22X2.44X12C | u | 0.30 | 26.05 | 7.82 |
| 18054 | Arena | m3 | 0.68 | 13.50 | 9.18 |
| 18055 | Ripio | m3 | 1.00 | 18.00 | 18.00 |
| 18056 | Agua | m3 | 0.23 | 0.85 | 0.20 |
| 18083 | Acero de refuerzo fc=4200kg/cm2 | kg | 50.00 | 0.81 | 40.50 |
| 18974 | Clavos 2", 2 1/2", 3", 3 1/2" | kg | 2.10 | 2.13 | 4.47 |
| 18975 | Alfajia 6x6x250 cm | u | 1.80 | 2.50 | 4.50 |
| 19623 | Plastiment BV-40 10 Kg - Sika DISENSA | u | 0.10 | 22.60 | 2.26 |
| 22034 | Puntal de madera de eucalipto | m | 3.60 | 1.12 | 4.03 |
| Total materiales | 149.09 | ||||
| 2. MANO DE OBRA | |||||
| Descripción | Unidad | Cantidad | Precio productivo | Costo total | |
| 15837 | Peón | Hora | 12.00 | 4.05 | 48.60 |
| 15838 | Albañil | Hora | 2.00 | ||
| 15839 | Operador de equipo | Hora | 4.00 | 4.10 | 16.40 |
| 15868 | Maestro de Obra | Hora | 2.00 | 4.33 | 8.66 |
| Total mano de obra | 73.66 | ||||
| 3. EQUIPO, MAQUINARIA Y HERRAMIENTAS | |||||
| Descripción | Unidad | Cantidad | Precio productivo | Costo total | |
| 18057 | Concretera 1 saco | Hora | 2.00 | 4.48 | 8.96 |
| 18058 | Vibrador de manguera | Hora | 2.00 | 4.06 | 8.12 |
| Herramientas menores % | 5.00% | 3.68 | |||
| Total equipo, maquinaria y herramientas | 20.76 | ||||
| 4. GASTOS GENERALES Y ADMINISTRATIVOS |
| 5. UTILIDAD |
| 6. IMPUESTOS | ||
| Total Precio Unitario de Colector H.A. S=1.00x1.00 M | 243.51 | |
Especificaciones técnicas:
RENDIMIENTO: 2.00 Horas/m