APU de Colector H.A. S=0.80x1.20 M
En :
1. MATERIALES | |||||
Descripción | Unidad | Cantidad | Precio productivo | Costo total | |
15914 | Cemento Fuerte Tipo GU Saco 50 Kg - Holcim DISENSA | saco | 6.50 | 7.68 | 49.92 |
16008 | Tablero TRIPLEX CORRIENTE 1.22X2.44X12C | u | 0.26 | 26.05 | 6.77 |
18054 | Arena | m3 | 0.59 | 13.50 | 7.97 |
18055 | Ripio | m3 | 0.86 | 18.00 | 15.48 |
18056 | Agua | m3 | 0.20 | 0.85 | 0.17 |
18083 | Acero de refuerzo fc=4200kg/cm2 | kg | 42.00 | 0.81 | 34.02 |
18974 | Clavos 2", 2 1/2", 3", 3 1/2" | kg | 1.90 | 2.13 | 4.04 |
18975 | Alfajia 6x6x250 cm | u | 1.60 | 2.50 | 4.00 |
19623 | Plastiment BV-40 10 Kg - Sika DISENSA | u | 0.08 | 22.60 | 1.81 |
22034 | Puntal de madera de eucalipto | m | 3.20 | 1.12 | 3.58 |
Total materiales | 127.76 |
2. MANO DE OBRA | |||||
Descripción | Unidad | Cantidad | Precio productivo | Costo total | |
15837 | Peón | Hora | 8.00 | 4.05 | 32.40 |
15838 | Albañil | Hora | 2.00 | ||
15839 | Operador de equipo | Hora | 4.00 | 4.10 | 16.40 |
15868 | Maestro de Obra | Hora | 2.00 | 4.33 | 8.66 |
Total mano de obra | 57.46 |
3. EQUIPO, MAQUINARIA Y HERRAMIENTAS | |||||
Descripción | Unidad | Cantidad | Precio productivo | Costo total | |
18057 | Concretera 1 saco | Hora | 2.00 | 4.48 | 8.96 |
18058 | Vibrador de manguera | Hora | 2.00 | 4.06 | 8.12 |
Herramientas menores % | 5.00% | 2.87 | |||
Total equipo, maquinaria y herramientas | 19.95 |
4. GASTOS GENERALES Y ADMINISTRATIVOS |
5. UTILIDAD |
6. IMPUESTOS | ||
Total Precio Unitario de Colector H.A. S=0.80x1.20 M | 205.18 |
Especificaciones técnicas:
RENDIMIENTO: 2.00 Horas/m