Grupos >
ESTRUCTURAS EN HORMIGON ARMADO >
En :
APU de Columnas P.B. de H.A. fc= 280 kg/cm2
En :
| 1. MATERIALES | |||||
| Descripción | Unidad | Cantidad | Precio productivo | Costo total | |
| 15914 | Cemento Fuerte Tipo GU Saco 50 Kg - Holcim DISENSA | saco | 9.00 | 7.68 | 69.12 |
| 15977 | Tabla dura de encofrado de 0.30 m. | u | 6.57 | 5.50 | 36.14 |
| 16096 | Alambre galvanizado No.18 | Kg | 1.85 | 2.54 | 4.70 |
| 16137 | Varilla corrugada 8-10-12 mm | 1.45 | 40.11 | 58.16 | |
| 16138 | Varilla corrugada 14mm o mayor | 5.65 | 40.11 | 226.62 | |
| 18054 | Arena | m3 | 0.58 | 13.50 | 7.83 |
| 18055 | Ripio | m3 | 0.72 | 18.00 | 12.96 |
| 18056 | Agua | m3 | 0.25 | 0.85 | 0.21 |
| 18912 | Cuartones de encofrado | u | 7.10 | 4.00 | 28.40 |
| 18913 | Tiras de encofrado | u | 3.67 | 1.88 | 6.90 |
| 18974 | Clavos 2", 2 1/2", 3", 3 1/2" | kg | 1.88 | 2.13 | 4.00 |
| 19623 | Plastiment BV-40 10 Kg - Sika DISENSA | u | 0.02 | 22.60 | 0.45 |
| Total materiales | 455.49 | ||||
| 2. MANO DE OBRA | |||||
| Descripción | Unidad | Cantidad | Precio productivo | Costo total | |
| 15837 | Peón | Hora | 15.26 | 4.05 | 61.80 |
| 15838 | Albañil | Hora | 2.18 | ||
| 15843 | Fierrero | Hora | 2.18 | 4.10 | 8.94 |
| 15844 | Carpintero | Hora | 2.18 | 4.10 | 8.94 |
| 15868 | Maestro de Obra | Hora | 2.18 | 4.33 | 9.44 |
| Total mano de obra | 89.12 | ||||
| 3. EQUIPO, MAQUINARIA Y HERRAMIENTAS | |||||
| Descripción | Unidad | Cantidad | Precio productivo | Costo total | |
| 18057 | Concretera 1 saco | Hora | 2.18 | 4.48 | 9.77 |
| 18058 | Vibrador de manguera | Hora | 2.18 | 4.06 | 8.85 |
| Herramientas menores % | 5.00% | 4.46 | |||
| Total equipo, maquinaria y herramientas | 23.07 | ||||
| 4. GASTOS GENERALES Y ADMINISTRATIVOS |
| 5. UTILIDAD |
| 6. IMPUESTOS | ||
| Total Precio Unitario de Columnas P.B. de H.A. fc= 280 kg/cm2 | 567.68 | |
Especificaciones técnicas:
RENDIMIENTO: 2.18 Horas/m3
(Cambiar país)