APU de Cisterna de H.A. fc= 280 kg/cm2
En :
| 1. MATERIALES | |||||
| Descripción | Unidad | Cantidad | Precio productivo | Costo total | |
| 15914 | Cemento Fuerte Tipo GU Saco 50 Kg - Holcim DISENSA | saco | 9.00 | 7.68 | 69.12 |
| 15977 | Tabla dura de encofrado de 0.30 m. | u | 15.21 | 5.50 | 83.66 |
| 16096 | Alambre galvanizado No.18 | Kg | 0.90 | 2.54 | 2.29 |
| 16137 | Varilla corrugada 8-10-12 mm | 2.50 | 40.11 | 100.28 | |
| 18054 | Arena | m3 | 0.57 | 13.50 | 7.70 |
| 18055 | Ripio | m3 | 0.72 | 18.00 | 12.96 |
| 18056 | Agua | m3 | 0.25 | 0.85 | 0.21 |
| 18912 | Cuartones de encofrado | u | 5.50 | 4.00 | 22.00 |
| 18974 | Clavos 2", 2 1/2", 3", 3 1/2" | kg | 0.75 | 2.13 | 1.60 |
| 19623 | Plastiment BV-40 10 Kg - Sika DISENSA | u | 0.02 | 22.60 | 0.45 |
| Total materiales | 300.25 | ||||
| 2. MANO DE OBRA | |||||
| Descripción | Unidad | Cantidad | Precio productivo | Costo total | |
| 15837 | Peón | Hora | 16.80 | 4.05 | 68.04 |
| 15843 | Fierrero | Hora | 8.40 | 4.10 | 34.44 |
| 15844 | Carpintero | Hora | 16.80 | 4.10 | 68.88 |
| 15868 | Maestro de Obra | Hora | 8.40 | 4.33 | 36.37 |
| Total mano de obra | 207.73 | ||||
| 3. EQUIPO, MAQUINARIA Y HERRAMIENTAS | |||||
| Descripción | Unidad | Cantidad | Precio productivo | Costo total | |
| 18057 | Concretera 1 saco | Hora | 2.40 | 4.48 | 10.75 |
| 18058 | Vibrador de manguera | Hora | 2.40 | 4.06 | 9.74 |
| Herramientas menores % | 5.00% | 10.39 | |||
| Total equipo, maquinaria y herramientas | 30.88 | ||||
| 4. GASTOS GENERALES Y ADMINISTRATIVOS |
| 5. UTILIDAD |
| 6. IMPUESTOS | ||
| Total Precio Unitario de Cisterna de H.A. fc= 280 kg/cm2 | 538.87 | |
Especificaciones técnicas:
RENDIMIENTO: 1.00 Horas/m3
(Cambiar país)